By the Climate & Energy Solutions team · Chico, CA, since 1985 Updated 6 min read
Quick answer
In most cases, yes. California's energy code generally requires a permit to replace an air conditioner, furnace or heat pump, and to install solar panels or a home battery. The permit comes from the building department that covers your address, which may be a city, a town or a county. Some HVAC changes also need third-party HERS testing. Always confirm with your local building department.
Key takeaways
- Replacing HVAC equipment and installing solar or batteries generally needs a permit in California.
- Your mailing address does not always tell you which building department covers your home.
- Some HVAC alterations can trigger independent HERS verification, such as duct leakage testing.
- Unpermitted work can raise questions at resale, with insurance, and sometimes means redoing the job.
Do you need a permit to replace an AC or furnace in California?
Generally, yes. California's Building Energy Efficiency Standards, known as Title 24, Part 6 and maintained by the California Energy Commission (CEC), treat replacing heating and cooling equipment as an alteration to the home. Alterations covered by the energy code typically need a permit and a final inspection, even when the new unit goes in the same spot as the old one.
The idea is to make sure the new equipment is installed safely and meets current efficiency rules. That covers things like equipment efficiency, duct condition and, in some cases, testing by an independent rater. The details depend on the project and get updated as the CEC adopts new code cycles, so this guide explains the general picture rather than the exact requirements.
This applies whether you are replacing a central air conditioner, a furnace or switching to a heat pump.
Which building department covers your address?
The authority having jurisdiction (AHJ) is the city, town or county building department that issues permits for your property. Inside city limits it is usually the city; outside them it is usually the county. The table below shows who it typically is across the area we serve.
One catch: a Chico or Oroville mailing address does not always mean you are inside city limits. Many homes with a city mailing address sit on unincorporated county land. Check by your street address or parcel number with the building department before you plan around one office.
| Where the home is | Usually the authority having jurisdiction | Good to know |
|---|---|---|
| Chico, inside city limits | City of Chico | Many Chico mailing addresses are outside city limits |
| Oroville, inside city limits | City of Oroville | Surrounding areas are often county land |
| Paradise | Town of Paradise | The Town runs its own building department |
| Durham, Magalia and other unincorporated Butte County | Butte County Department of Development Services | Covers county areas outside city and town limits |
| Orland, inside city limits | City of Orland | Homes outside city limits fall under Glenn County |
| Hamilton City and unincorporated Glenn County | Glenn County | Hamilton City is unincorporated |
| Corning, inside city limits | City of Corning | Homes outside city limits fall under Tehama County |
| Los Molinos and unincorporated Tehama County | Tehama County | Los Molinos is unincorporated |
What is HERS verification, and when does it come up?
HERS stands for Home Energy Rating System. A HERS rater is an independent, certified third party, separate from both your contractor and the city or county inspector. Under the energy code, some HVAC alterations can require a rater to verify parts of the work before the permit is closed.
The most common example is duct leakage testing, where the rater pressurizes the duct system and measures how much air escapes. Depending on the project, other checks, such as refrigerant charge or airflow, may also be required. Whether your project triggers HERS verification depends on what is being changed, so ask the building department or your contractor early, not after the work is done.
Older homes with ducts in a hot attic are where this tends to matter most, because leaky ducts may need repair before the test can pass.
What about solar panels, batteries and generators?
Rooftop solar and home battery systems generally need a building permit and an inspection from the same local building department. The review typically looks at the electrical work, how the panels attach to the roof, and fire-safety access on the roof. Battery locations and clearances are reviewed too.
Solar adds a second step: before the system can be switched on, PG&E has to approve the interconnection to the grid. Passing the local inspection and getting utility approval are separate milestones. Standby generators and EV chargers commonly need permits as well.
What are the risks of skipping the permit?
It can be tempting to skip a permit to save time, but unpermitted work tends to cost more in the end.
- Resale questions. Buyers, inspectors and agents may ask for permit records, and missing ones can complicate a sale.
- Appraisal questions. An appraiser may not credit equipment or solar that has no permit history.
- Insurance questions. After a fire or water claim, an insurer may ask whether the work was permitted and inspected.
- Redoing work. A building department can require walls or ceilings opened, or work corrected, to inspect it after the fact.
- Incentive problems. Some rebate and incentive programs ask for proof of a permit before paying.
- Safety. Inspections exist to catch gas, venting and electrical mistakes that are not visible to a homeowner.
How do you check what your project needs?
A few steps before the work starts saves a lot of trouble later.
- Confirm which building department covers your parcel, not just your mailing address.
- Ask that department what permits and inspections apply to your project.
- Ask your contractor whether HERS verification is likely and who arranges it.
- Ask us during your estimate which permits your project needs, so it is part of the plan from the start.
- Keep the final inspection record with your equipment paperwork.
Is this legal advice?
No. This guide is educational, not legal advice. Permit rules, energy code requirements and local processes change, and every property and project is different. The building department with jurisdiction over your address is the authority on what your project requires. For a specific situation, contact that department directly.
When you are planning a project with Climate & Energy Solutions, ask us during your free online estimate follow-up or your in-home visit which permits your project needs, and we will walk through it with you.
Frequently asked questions
Do I need a permit to replace my AC with the same size unit?
Generally, yes. California's energy code treats an equipment changeout as an alteration, even when the new unit is the same size and goes in the same place. Some projects may also need HERS verification. Confirm the exact requirements with the building department that covers your address.
How do I know if my home is in the city or the county?
Your mailing address is not a reliable guide; many homes with a Chico or Oroville address are on unincorporated county land. The building department can confirm by street address or parcel number, and county parcel tools usually show it too. Check before you plan the project.
What is a HERS test?
A HERS test is a check by an independent, certified rater, separate from your contractor and the inspector. For HVAC work it often means duct leakage testing, and sometimes refrigerant charge or airflow checks. Whether your project needs one depends on what is changing, so ask early.
Does solar need a permit if it is on my own roof?
Generally, yes. Rooftop solar and home batteries typically need a building permit and inspection from your local building department, and PG&E must approve the interconnection before the system is turned on. Requirements vary by jurisdiction, so confirm with the department that covers your address.
Your next step
Talk it through with a local team
Planning an HVAC, solar or battery project and not sure what permits apply? Call or text (530) 891-6787, Monday–Friday, 8 AM–5 PM, and ask us during your estimate which permits your project needs.
Keep reading
- Permits & Code · Learn The R-410A Phase-Out: What the New A2L Refrigerants Mean for You
- Cooling & AC · Compare Should You Repair or Replace Your Air Conditioner?
- Maintenance & Hiring a Pro · Decide What to Expect From an HVAC Estimate
- Solar, Batteries & Backup Power · Compare Solar PPA vs. Buying Solar: Which Fits Your Home?
Sources & further reading
- California Energy Commission — Building Energy Efficiency Standards (Title 24, Part 6) (opens in a new tab)
- City of Chico (opens in a new tab)
- City of Oroville (opens in a new tab)
- Town of Paradise (opens in a new tab)
Who wrote this. This guide was written by the team at Climate and Energy Solutions Inc. (CSLB #807511), a family-owned heating, cooling and solar company in Chico, California, since 1985. We are a Mitsubishi Electric Diamond Contractor Elite and a Day & Night Elite Dealer. It is general information for North Valley homeowners, not a diagnosis of your system. Rebates, codes and utility rules change, so confirm specifics with us, your utility or your building department. About us.